The most recent version of the Bicycle Master Plan implementation plan included many gaps in Southeast Seattle’s bike network and eliminated miles of planned bike lanes in the southern half of the city.
Tomorrow afternoon, the Seattle Department of Transportation will release the latest version of the Bike Master Plan Implementation Plan, which outlines the bike projects the city plans to build and study through 2024, according to sources familiar with the latest version of the plan.
In response to community feedback urging the city to restore some of the cuts SDOT proposed to bike lanes in Southeast Seattle, the new plan will reportedly include a new mile-long bike lane along Martin Luther King Jr. Way S. between the Mount Baker light rail station and I-90, as well as “pre-planning” for a protected bike lane (PBL) along MLK to Southeast Seattle; a bike lane along Beacon Ave. from the Jose Rizal Bridge in the International District to 39th Ave. S. about five and a half miles away, and some sort of new connection between downtown and Georgetown (where heavy freight traffic along Airport Way has made putting a bike lane there a political and logistical challenge).
The new update will also reportedly scale back plans for a protected bike lane on Fourth Avenue—already delayed three years from the original 2018 opening date—by replacing the planned two-way protected lane on the east side of the street with a one-way (northbound) protected lane on the west side, where there is currently an unprotected one-way bike lane. SDOT justified delaying the bike lane last year by saying that it didn’t want to risk delaying transit along Fourth Avenue during the “period of maximum constraint,” when much of downtown is under construction. The two-way bike lane was rescheduled to open in 2021, once light rail trains begin running to Northgate.
Support The C Is for Crank
Hey there! Just a quick reminder that this entire site, including the post you’re reading, is supported by generous contributions from readers like you, without which this site would quite literally cease to exist. If you enjoy reading The C Is for Crank and would like to keep it going, please consider becoming a sustaining supporter. For just $5, $10, or $20 a month (or whatever you can give), you can help keep this site going, and help me continue to dedicate the many hours it takes to bring you stories like this one every week. This site is my full-time job. Help keep that work sustainable by becoming a supporter now! If you don’t wish to become a monthly contributor, you can always make a one-time donation via PayPal, Venmo (Erica-Barnett-7) or by mailing your contribution to P.O. Box 14328, Seattle, WA 98104. Thank you for reading, and I’m truly grateful for your support.
SDOT’s initial version of the implementation plan, which came out in March, eliminated miles of long-planned protected bike lanes , particularly in Southeast Seattle—the area of the city that the Seattle Bicycle Advisory Board emphasized top priorities. (The mayor’s office asked the board to come up with a list of priority projects after SDOT announced that the city would not be able to complete all of the projects that had been funded in the Move Seattle levy last year.)
Although the bike board specifically identified Southeast Seattle as the area most lacking in safe bike connections to the rest of the city, the update eliminated a greenway on Beacon Ave. S and a protected bike lane on Rainier Ave. S., one of the deadliest street for cyclists and pedestrians in the city, leaving Southeast Seattle with what Seattle Neighborhood Greenways’ director Gordon Padelford called “a few scattered hilly segments” of bike lanes. SDOT, with assistance from the Department of Neighborhoods, held a series of neighborhood meetings where participants identified their top priorities; at the one I attended, in South Beacon Hill, residents said they were worried that Mayor Durkan and SDOT weren’t willing to risk political controversy to build safe, convenient bike connections between Southeast Seattle and downtown.
The proposals to begin “pre-planning” on some north-south streets seems like an acknowledgement of those concerns (as does the proposal to actually build a mile of bike lane between Mount Baker and I-90). As usual, though the proof will be in whether these bike lanes actually get built, or whether they end up gathering dust along with much of the original Bike Master Plan.
Your mileage may vary. This grand total, for example, is actually more like 30. (Full list available here.)
As I reported in March, the city’s updated bike master plan implementation plan (sorry for the unwieldy mouthful, but that’s what it’s called) eliminates more than just the list of projects the Seattle Department of Transportation chose to highlight on pages 36-37 of the update. It also quietly eliminated nearly a dozen projects without including them on the list of official cuts. (I came up with this list by manually checking every project in the 2017 plan against every project in the 2019 update, then figuring out which projects went unmentioned in the 2019 plan.) Those missing projects include protected bike lanes around the city—from the University District to SoDo to Beacon Hill to the Rainier Valley—as well as basic bike lanes and neighborhood greenways. After compiling the list, I sent it to the Seattle Department of Transportation and asked them where the projects went.
Here’s what they had to say.
1. 11th / 12th Ave NE 2018 Paving (1.94 miles)
This project, originally a 1.94-mile bike lane along 11th and 12th Ave. NE between the University Bridge and Roosevelt, is partly accounted for under the new list of “Projects Removed,” which includes a half-mile protected bike lane along 12th between NE 67th and NE 75th Streets. The remainder of this bike lane is, according to SDOT spokesman Ethan Bergerson, accounted for as part of the “Roosevelt RapidRide multimodal corridor,” which could begin construction as soon as 2021.
The 2019 bike plan update describes the Roosevelt RapidRide project as “fully funded through construction pending [Federal Transit Agency] funds.” According to the Move Seattle Levy “reassessment” last year, which examined which of the projects promised in the 2015 levy could actually be completed given costs that turned out to be higher than the original estimates and federal funding constraints, “[a]ll budgeted funds [for Roosevelt RapidRide] are not yet secured. In addition, uncertainty related to Small Starts funding persists, particularly with regards to the schedule to secure a funding commitment from FTA. SDOT anticipates having to continue to advance the project at SDOT’s risk until at least late 2020 before securing funding.”
2. N 50th St 2019 Paving (0.64 miles)
SDOT all but eliminated this planned 0.64-mile protected bike lane connecting Phinney and Green Lake along NE 50th St—first by cutting it down to 0.27 miles (and pushing it back a year), then by reducing the scope of the project, which will now consist of two short segments of slightly wider, unprotected bike to the east and west of Aurora Ave. N. SDOT spokesman Ethan Bergerson says the city decided not to move forward with the original plan because “the roadway is not wide enough to accommodate protected bike lanes. Widening the bike lanes allows us to increase safety while also retaining parking in the area.” The need to preserve parking is the same argument that ultimately doomed a long-planned protected bike lane on 35th Ave. NE, which was killed after activists complained that eliminating on-street parking would destroy local businesses.
The bike lanes, according to Bergerson, will be one additional foot wide. Here’s the city’s fact sheet on the project.
3. N / NE 40th St 2019 Paving (1.12 miles)
This 1.12-mile unprotected bike lane on 40th St., which was supposed to be completed this year, gets a brief and partial mention in the bike plan update, which mentions that a 0.29-mile protected bike lane on N 40th has been eliminated from the package “due to design constraints & funding risk.” Bergerson says this PBL and the longer unprotected bike lane are the same project, although 0.83 miles of the original bike lane remain unaccounted for in the new update.
According to Bergerson, “During our recent outreach, we heard concerns about the plan to add a protected bike lane. In addition to concerns from neighbors and businesses about parking removal and loading access needs, we also heard safety concerns about the design from people who bike through this area. … Since there are nearby alternative east/west bike routes (Burke Gilman Trail and the N 44th St Neighborhood Greenway), we postponed the N 40th PBL to evaluate other potential spot connection improvements on or near N 40th St.” Seattle bike advocates generally prefer protected bike lanes over neighborhood greenways because they offer physical protection from cars, don’t force cyclists onto circuitous parallel paths full of obstacles like traffic circles and speed bumps, and make it easy for people to ride bikes to destinations along arterials, rather than on parallel paths that may be many blocks away from where they want to go.
Bergerson says this project—described in the 2017 plan as a 0.25-mile neighborhood greenway along N 83rd St. between Fremont Ave. N and Aurora Ave. N—has been renamed the “Green Lake to Interurban Connection,” to “highlight the connection between the Green Lake PBLs and the Interurban/Fremont Ave NGW.” Although the 2019 draft plan lists this as a 0.38-mile project, Bergerson said that was in error, and the final version of the plan will reflect that the project is 0.25 miles long.
Support The C Is for Crank
If you like the work I’m doing here, and would like to support this page financially, please support me by becoming a monthly donor on Patreon or PayPal. For just $5, $10, or $20 a month (or whatever you can give), you can help keep this site going, and help me continue to dedicate the many hours it takes to bring you stories like this one every week. This site is funded entirely by contributions from readers, which pay for the time I put into reporting and writing for this blog and on social media, as well as reporting-related and office expenses. If you don’t wish to become a monthly contributor, you can always make a one-time donation via PayPal, Venmo (Erica-Barnett-7) or by mailing your contribution to P.O. Box 14328, Seattle, WA 98104. Thank you for reading, and I’m truly grateful for your support.
5. One Center City – Spring Street BL (five blocks)
This five-block bike lane from 4th Ave. to 9th Ave. now appears on a list of “completed” projects, although the project that was actually completed was a scaled-back three-block version of the original project.
Update: In a followup email, Bergerson says the city has “additional paving work planned in this area” and will “reinstall and extend the PBL from 1st Ave to 9th Ave once the pavement construction is complete.”
6. Madison RapidRide (G Line) Complementary Route (20-22 blocks)
This approximately 1.5-mile bike facility between Boylston and roughly Martin Luther King Way S, the details of which were listed as “TBD” in 2017, was removed from the project list and “replaced,” in some places, “with other routes serving similar goals,” according to Bergerson. The “replacement” projects that roughly parallel the original proposal include a three-block stretch of bike lane on Union Street between 11th and 14th, one block of which has already been completed by a private developer, and a 0.67-mile protected lane that’s supposed to be finished this year as part of the Madison Multimodal Corridor project. Four other projects related to the (possibly former) Madison Street bus-rapid transit project are also listed as “removed” in the update, but none appear to exactly parallel the original 2017 project.
7. One Center City – Bell and/or Blanchard Protected Bike Lane
Bergerson says this six-to-seven-block bike lane project, which was originally scheduled for completion in 2020, will now be finished in 2021 and was ” left out of the draft Implementation Plan due to a copying and pasting error.”
8. One Center City – Vine Street
This six-block bike lane, originally scheduled for completion in 2020, should have been included in the list of project cuts, Bergerson says. He says SDOT will add this project to the list of projects removed from the plan.
9. S Spokane St 2020 Paving
This 0.39-mile bike lane on Beacon Hill was also supposed to be finished in 2020, and also should have been included in the list of project cuts. Bergerson says SDOT will add it to the list of removed projects.
10. NGW Connections (2018-2021) (4 miles)
This item, which referred to a total of about 4 miles of unspecified neighborhood greenways throughout the city, has been removed. According to Bergerson, the ill-defined greenways have been replaced in the latest plan by more specific “Safe Routes to School neighborhood greenway connections.” These projects—which include two greenways, totaling 1.32 miles, that were included in both the 2017 and 2019 plans—add up to about 9 miles of new neighborhood greenways.
11. 12th Ave S Protected Bike Lane (0.53 miles)
The new plan eliminates most of a protected bike lane along 12th Avenue S, including a segment between S. King Street and Yesler Way that passes by Bailey Gatzert Elementary School. In place of that 0.53-mile protected bike lane, the city will build a quarter-mile protected lane from the Jose Rizal Bridge (near the original southern terminus of the bike lane) to S. King Street. Advocates who noticed the cut have pointed out that the 12th Avenue south of Yesler includes many bike collision hot spots.
The city will hold a series of four evening open houses on the proposal, starting on April 23. Details on each of the meetings are available on the city’s website.
Dozens of bike safety advocates lined up in city council chambers this afternoon to express their frustration at a Bicycle Master Plan update from Mayor Jenny Durkan’s Seattle Department of Transportation that eliminates dozens of projects, replaces planned protected bike lanes with neighborhood greenways on distant, often hilly, parallel streets, and gives especially short shrift to neighborhoods in Southeast Seattle, where two of the Seattle Bicycle Advisory Board’s top-priority projects, on Rainier Ave. S and Beacon Ave. S, have been cut. Just prior to the meeting, the advocates held a rally and press conference in the lobby of City Hall, where council members Teresa Mosqueda and Mike O’Brien joined them in condemning the cuts.
Last year, SDOT announced significant cuts to many of the projects included in the $930 million Move Seattle levy, to reflect reduced federal funding and higher cost estimates for some projects.Meg Wade, from the climate action group 350 Seattle, talked about the abuse she has received from drivers as a queer cyclist and pedestrian. “I have been called a cunt; I have been called a bitch taking up too much space on the road; I have stepped into a crosswalk and asked a driver to move their car and been told ‘I am sick of you people’ I have been told ‘Fucking get out of my way.’ What this says is, it is okay for the harassment to continue.” Wade continued, her voice shaking: “It is astonishing to me that the mayor, who comes out of the gay community, would not understand that saying… ‘Go hide out of the public vision; get out of our public spaces’—that she wouldn’t understand the similarities” between anti-LGBT harassment and harassment of cyclists.
“Working-class people, middle-class people, families with little children, elderly individuals, community members—all of them have spoken [against the cuts]. When the mayor says it’s about community engagement, it’s about public feedback—well, whose feedback are you actually listening to?”
Immediately after Wade spoke, two cyclists, Apu Mishra and Tamara Schmautz, stood up to dramatically “mourn the loss” of three plans previously adopted by the city—the Bicycle Master Plan, the Climate Action Plan, and the Complete Streets—by destroying copies of each document in a hand-cranked portable shredder.
Members of the Seattle Bicycle Advisory Board, including its current co-chair, Emily Paine, expressed dismay that the plan labeled 13 of the eliminated projects “SBAB removed,” implying that the bike board had recommended those projects for removal. Some of those projects, Paine said, were not only “not recommended by SBAB to be removed,” they “were actually given our highest endorsement,” including a protected bike lane on Beacon Hill and a PBL on Rainier Avenue South.
SDOT attempted to walk back the “SBAB removed” designation on Tuesday, calling it an inadvertent error and apologizing for the confusion. (SDOT traffic engineer Monica DeWald said, “We should have rephrased that to ‘SBAB prioritized but funding limited,’ just so we sent the message that it was still an SBAB top priority but we just didn’t have the funding.”) But agency staffers were undoubtedly aware that the list of cuts included some of the bike board’s top priorities when they came up with the list. In an email to bike board members and SDOT staff, including DeWald, from last November, SDOT senior transportation planner Serena Lehman compiled a list of the board’s top priorities, which included both the Beacon Avenue and Rainier Ave. bike lanes. SDOT has not elaborated on why these two top-priority projects have been cut other than to say that the city doesn’t have the money to build them.
Bike board members also expressed concern Tuesday that SDOT has designated about half of all the bike projects that are scheduled for completion between 2019 and 2024 projects as having high levels of “risk,” which they worried might provide cover to remove them from the plan. “A pattern has emerged in this administration of delaying and eliminating bike lanes that prove challenging or controversial,” bike board member Patrick Taylor said. “When I look at the implementation plan, I see most of the projects listed as ‘risky,’ which in an administration that does not have the gumption to follow through with projects designated as challenging, I view as concerning.”
“Our perception on the Bike Advisory Board is that this administration does not care what we think, and that when we send letters, we might as well send them as a paper airplane.”
Council members, including O’Brien, committee chairman Rob Johnson, and Kshama Sawant, expressed frustration that the mayor had rolled the bike plan back so dramatically. Sawant, who has not historically been among the council’s most vocal bike advocates, was particularly vociferous, arguing that it was “meaningless” for SDOT staffers to tout the city’s progress on bike infrastructure “at the same time that the mayor’s office and SDOT leadership has dealt a significant blow to the whole plan. … Working-class people, middle-class people, families with little children, elderly individuals, community members—all of them have spoken [against the cuts], Sawant said. “So I don’t really understand. When the mayor … says it’s about community engagement, it’s about public feedback—well, whose feedback are you actually listening to?” Sawant’s comments were a rebuke to activists who helped defeat a long-planned protected bike lane on 35th Ave. NE, who argued that only “privileged” white people ride bikes or care about safe bike infrastructure.
Members of the Move Seattle Levy Oversight Committee hit on many of the same themes at their monthly meeting Tuesday night, and discussed issuing formal recommendations to the council in response to the scaled-back plan. Committee member Joseph Laubach, who noted that the new plan delivers only about 60 percent of the miles of new bike lanes, trails, and greenways included in the original levy, called the new strategy “unfair” even in light of the Move Seattle “reset.” Taylor, who also sits on the Move Seattle committee, noted that the bike board prioritized projects in South Seattle neighborhoods like Beacon Hill and the Rainier Valley precisely because they connected those historically neglected neighborhoods to downtown. “All the projects that rose to the top of our list for extra emphasis are in Southeast Seattle… and those were the projects that disappeared without a trace,” he said. [Editor’s note: This paragraph initially said that the new plan eliminates 60 percent of the new bike lane-miles; in fact, it eliminates 40 percent and preserves 60 percent.]
Both O’Brien, who attended Tuesday night’s committee meeting, and Taylor, who noted that the bike board itself will discuss the new plan at its own meeting tomorrow night, urged the committee to consider making a formal recommendation to the council. “Our perception on the Bike Advisory Board is that this administration does not care what we think, and that when we send letters, we might as well send them as a paper airplane,” Taylor said. “Having this board’s letter as well might elevate [the concerns] to a higher level.”
Support The C Is for Crank
If you like the work I’m doing here, and would like to support this page financially, please support me by becoming a monthly donor on Patreon or PayPal. For just $5, $10, or $20 a month (or whatever you can give), you can help keep this site going, and help me continue to dedicate the many hours it takes to bring you stories like this one every week. This site is funded entirely by contributions from readers, which pay for the time I put into reporting and writing for this blog and on social media, as well as reporting-related and office expenses. If you don’t wish to become a monthly contributor, you can always make a one-time donation via PayPal, Venmo (Erica-Barnett-7) or by mailing your contribution to P.O. Box 14328, Seattle, WA 98104. Thank you for reading, and I’m truly grateful for your support.
South Seattle’s Bike Master Plan projects have been reduced to “a few scattered hilly segments,” according to one bike advocate,
Days after announcing that the city had decided to kill a long-planned protected bike lane on 35th Ave NE in response to “many concerns we’ve heard from the community,” there was more bad news for cyclists. Three days later, the Seattle Department of Transportation released an update to the city’s Bike Master Plan that eliminates additional protected lanes, pushes other bike projects back several years or indefinitely, and contains no reference to about a dozen projects that were in the most recent update, back in 2017.
Last year, SDOT announced significant cuts to many of the projects included in the $930 million Move Seattle levy, which voters approved in 2015, to reflect reduced federal funding and higher cost estimates for some projects. (In the implementation plan, SDOT says the original cost estimates were not “realistic.”) Although a council resolution requires the agency to provide an updated implementation plan for the bike plan every year, SDOT skipped last year, making this the first update since the reset. This also means that any comparisons are necessarily between the 2017 implementation plan and the 2019 plan that was just released—an exercise the mayor’s office has suggested does not compare apples to apples. However, even within the reduced scope of the new plan post-“reset,” it’s possible to glean the city’s priorities (protected bike lanes on arterials, the widely accepted gold standard for safe bike infrastructure, are largely out; neighborhood greenways, which typically consist of sharrows and speed humps on slower side streets parallel to main streets, are largely in.)
Support The C Is for Crank
If you like the work I’m doing here, and would like to support this page financially, please support me by becoming a monthly donor on Patreon or PayPal. For just $5, $10, or $20 a month (or whatever you can give), you can help keep this site going, and help me continue to dedicate the many hours it takes to bring you stories like this one every week. This site is funded entirely by contributions from readers, which pay for the time I put into reporting and writing for this blog and on social media, as well as reporting-related and office expenses. If you don’t wish to become a monthly contributor, you can always make a one-time donation via PayPal, Venmo (Erica-Barnett-7) or by mailing your contribution to P.O. Box 14328, Seattle, WA 98104. Thank you for reading, and I’m truly grateful for your support.
Of two dozen projects that were supposed to be completed last year, only one —a 0.65-mile neighborhood greenway serving Eagle Staff Middle school in north Seattle—appears to have been completed on the original schedule. None of the 19 projects originally scheduled for completion in 2019 are on track to be done this year. Instead, they are pushed forward to 2020 or 2021—the final years included in the update. And the majority of the projects that were originally scheduled for completion in 2020 and 2021 are no longer being built, either because they have been explicitly removed from the plan or because they no longer appear on the list.
This last group of projects include planned protected bike lanes on Greenwood Ave. N, Broad Street, Fauntleroy Ave. SW, and Montlake, as well as planned neighborhood greenways on Beacon Ave. S and a protected bike lane on Rainier Ave. S., one of the deadliest street for cyclists and pedestrians in the city. The southeast corner of the city, which also happens to be one of the poorest and most racially diverse areas of Seattle, is left with what Seattle Neighborhood Greenways leader Gordon Padelford called “a few scattered hilly segments.”
WOW… None of the 3 main North-South routes in SE Seattle (Rainier, MLK, & Beacon Ave) will get a safe place to bike over the entire lifetime of the @LetsMoveSeattle levy. Instead, Rainier Valley and Beacon Hill will get a few scattered hilly segments. https://t.co/naqyY3cVsHpic.twitter.com/H1GqS3geOT
In contrast, all but one of the projects that were supposed to be finished in 2017 under the original plan have been completed, and all but three of those were finished on time (the three exceptions were finished in 2018). The one project that was not completed was the Fourth Avenue protected bike lane, which Mayor Jenny Durkan announced the city was delaying last year.
The most common reason given for delays to projects that are being finished late is “weather.” The most common reason given for removing projects from the plan is “SBAB removed”—a reference to the Seattle Bicycle Advisory Board.
Durkan spokesman Mark Prentice says “SBAB removed” refers to “projects that SBAB opted not to prioritize. This does not mean that SDOT and SBAB do not consider these worthy projects, but just that based on resources and preferred connections, these did not rise to the top of the list.”
However, as member Patrick Taylor noted on Twitter, the bike board actually did recommend several projects, including the Beacon Avenue greenway and the Rainier protected bike lane, that were nonetheless cut from the list. (Instead of a protected bike lane, the plan now calls for a “focus on spot transit improvements.”)
As other have said we didn’t vote to remove, we just listed things as not a priority for this plan. We voted Beacon Ave as the highest priority and I don’t see it.
Asked about the Beacon Ave. project, which was included for study in the 2018 draft implementation that was never released, Prentice said, “The current board members thought it was an important connection but due to the limited funding to select projects (and the fact that there is an existing separated ped path) they dropped it for other projects.” The project, Prentice says, “would have looked at upgrading the pedestrian path in the median to a multi-use path and review of in-street minor sections on roadway.”
Advocates have also pointed out that at least two projects appear to be double-counted as being completed in both 2017 and 2018—a protected bike lane on Banner Way near Maple Leaf and a PBL along S. Dearborn St. Both projects are counted toward the total “miles delivered” in each year, contributing to a total of 10.81 miles of new bike facilities in 2017, and 10.26 miles in 2018. The city painted buffered bike lanes (bike lanes with painted double stripes to visually separate them from cars) on Banner Way in 2017 and converted them to (arguably) protected bike lanes (still double-striped lanes, but with flexible posts to let drivers know when they are veering into the lane) in 2018. To date, the Dearborn project has not been completed.
Prentice says counting buffered-to-protected bike lane projects twice was “the direction back in 2017,” adding, “Both projects (Banner and Dearborn) are shown as PBLs in our 2018 six-month progress report that went to Council. No one mentioned anything about double counting when that document was posted.”
And he points out that the new plan explicitly does not “double count” three neighborhood greenways that are scheduled for “upgrades” this year. He said he would have to get back to me on the Banner Way and Dearborn projects. Prentice also said he would get back to me with more details about a list of 11 projects that appear to have disappeared between the 2017 and 2019 versions of the plan. I’ll update this post when I hear back.
The city council’s transportation committee will get a briefing—and take public comment—on the new implementation plan at 2:00 this coming Tuesday afternoon in council chambers.
Learn to trust the Crank: As I reported this morning, Mayor Jenny Durkan’s office met with advocates for and against a proposed one-way protected bike lane on 35th Ave. NE to tell them that the city does not plan to move forward with the long-planned lane.
According to a notice from the Seattle Department of Transportation, SDOT is going with an “alternative design” that includes no bike lane at all. The protected bike lane has been a part of the city’s adopted bike master plan since 2014. Recently, a group of opponents has argued that adding a protected bike lane on one side of the street would harm businesses by removing parking spaces—despite the fact that a city parking utilization study found that only 40 percent of the parking spaces near the proposed bike lane were occupied on an average weekday.
Ironically, the new design actually eliminates just as much parking as the bike lane plan, which was already designed, contracted, and shovel-ready. In a statement, SDOT said cyclists could use an existing “parallel neighborhood greenway” several blocks away which bike advocates called an inadequate substitute for a protected lane on an already existing major bike arterial.
The most recent report on the Move Seattle levy revealed that the Seattle Department of Transportation has continued to fall behind on plans to build out the bike network laid out in the 2014 Bike Master Plan, particularly when it comes to protected bike lanes.
Here’s SDOT’s statement on the decision. I have calls out to SDOT and the mayor’s office and will update this post with any additional information.
Since the early stages of the 35th Ave NE Project, we’ve heard support from the community for changes to the street that improve safety. When the project began, the goal was to better organize the street, increasing safety for everyone. To meet this goal, we proposed a design that included bike lanes consistent with recommendations in the Bike Master Plan.
In response to the feedback we heard about the design, and based on industry best practices, data analysis, and continued conversations with the community, we’ve chosen to move forward with a new design that includes 1 travel lane in each direction, a center turn lane (north of 65th) and parking maintained on the east side of the street (between NE 47th and NE 85th streets).
Better street design can lead to safer streets. The new design helps us improve safety and operations for all travelers on 35th by providing a dedicated space for turning vehicles. We’ve seen decreased vehicle speeds and decreased collision rates on streets with 1 lane in each direction and a center turn lane. Examples include NE 75th St, NE 125th St, and Nickerson St. By slowing vehicle speeds and better defining the travel lanes, this helps increase safety for everyone on 35th, including people crossing the street. While there would be no protected bike lanes on 35th, people riding in the street would still benefit from slower vehicle speeds and clearly defined travel lanes. We will also be making enhancements to the parallel neighborhood greenway on 39th Ave NE that provides a route for people that prefer to bike on a quieter street.
To make space for the center turn lane, parking will be maintained on the east side of the street, instead of both sides. Throughout this project, we’ve worked with businesses and religious organizations along 35th to better understand parking, loading, and access needs. With the new design, we have decided to prioritize parking on the east side of the street. This decision is based on community feedback and the location of several existing load zones and ADA parking spaces on the east side of the street. We’ve heard these spaces are critical for people with limited mobility that are attending services at the religious institutions on 35th.
The new design addresses many concerns we’ve heard from the community however, we’ve also heard requests for additional enhancements along the corridor. SDOT is evaluating these requests and will share more information as we have it.
Support The C Is for Crank
If you like the work I’m doing here, and would like to support this page financially, please support me by becoming a monthly donor on Patreon or PayPal. For just $5, $10, or $20 a month (or whatever you can give), you can help keep this site going, and help me continue to dedicate the many hours it takes to bring you stories like this one every week. This site is funded entirely by contributions from readers, which pay for the time I put into reporting and writing for this blog and on social media, as well as reporting-related and office expenses. If you don’t wish to become a monthly contributor, you can always make a one-time donation via PayPal, Venmo (Erica-Barnett-7) or by mailing your contribution to P.O. Box 14328, Seattle, WA 98104. Thank you for reading, and I’m truly grateful for your support.
1. The latest quarterly report on the Move Seattle Levy, which The C Is for Crank obtained in advance of a Move Seattle Oversight Levy Committee meeting on Thursday, reveals that the Seattle Department of Transportation has continued to fall behind on plans to build out the bike network laid out in the 2014 Bike Master Plan, particularly when it comes to protected bike lanes. According to the report, because of “ongoing challenges with cost estimate increases, packaged-contracting approach, and contractor delays,” SDOT will “not meet annual targets” for bike-safety improvements—an understatement, given that many of the projects that were supposed to have been completed or underway this year have been delayed multiple times, some since 2016, the first year the levy was in effect. (The report also includes updates on other levy projects, including sidewalks, street paving, and bridge projects.)
The report lists seven bike projects as being completed in 2018, including two that were “2017 target[s]” (full list above). These include 1.88 miles of protected bike lanes and 7.47 miles of neighborhood greenways—markings and traffic-calming measures on streets that parallel arterial streets. This represents a significant shortfall from the 10.43 miles of protected bike lanes and 12.47 miles of greenways that SDOT had planned to build this year. Protected bike lanes are typically more controversial than neighborhood greenways, because they take up space on arterial roads that was previously occupied by (parked or moving) cars; witness the battle over a long-planned bike lane on 35th Avenue Northeast, which is on this year’s list of planned but uncompleted projects. (More on that below).
However, a closer look at all five of the projects the report cites as having come in on schedule in 2018 reveals that SDOT is further behind on building greenways and, especially, protected bike lanes than the report makes it appear. Of the five projects, only one—a 0.65-mile stretch of greenway on N. 92nd Street—was originally scheduled for construction in 2018. The rest were delayed projects from previous years. “If we’re going to live up to our climate goals, our equity goals, our safety goals, we have a lot of work left to do,” Neighborhood Greenways director Gordon Padelford, who received a copy of the report, says.
For example: A 5.45-mile stretch of greenway paralleling Rainier Ave. S., which the report lists as a completed 2018 project, was originally supposed to be built back in 2016, under to the city’s adopted Bike Master Plan, but was pushed back, first to 2017, and then to this year. (SDOT’s third-quarter report for last year—the equivalent of the report that’s being released this week—lists the project as “pushed to 2018.”) Similarly, a 0.39-mile protected bike lane on 7th Avenue, in downtown Seattle, that the report counts as a 2018 project was originally supposed to be finished in 2017. Another protected bike lane on S. Dearborn Street, which has not been completed and is listed as “in progress,” was originally supposed to be built by 2016.
Oversight committee member Brian Estes says, echoing the report, that some of the delays were unavoidable, due to issues with contractors, a concrete driver strike in September, and other factors. But, he says, “political considerations” also contributed to delays in building out bike infrastructure in the center city (the City Center Bike Network and the One Center City plan) under both former mayor Ed Murray and current Mayor Jenny Durkan. In August, the oversight committee sent a lengthy letter to Durkan and the council outlining other factors that, in their view, contributed to problems delivering on all the projects promised in the levy, including SDOT’s “organizational structure and culture,” “lack of transparency and failure to act,” and the fact that Durkan still had not appointed a permanent director of SDOT. (The agency is currently on its second interim director since Durkan took office in 2017).
A spokeswoman for SDOT says that a new work plan, which will also be released on Thursday, will provide much more detailed information about how the city plans to complete the outstanding levy projects. The oversight committee has not yet received a copy of that work plan, which, according to an email an SDOT staffer sent to stakeholders, was held up because staffers were out of town over Thanksgiving and due to the need for “coordination with the Mayor’s Office.” In the email, the staffer characterized the third-quarter report, not the work plan, as “the main topic for Thursday’s meeting.”
2. A series of “facilitated conversations” between advocates for and against a planned bike lane along 35th Ave. NE between Wedgwood and Ravenna did lead to some consensus around a set of safety improvements in the corridor—lower speed limits, new crosswalk markings, and the like—but no agreement on whether to build the protected bike lane, which has been in the Bike Master Plan since 2014. Opponents of the bike lane have argued that it will harm businesses who need on-street parking (in fact, a parking utilization study showed that, at most, 40 percent of spaces are occupied); that it will lead to more collisions with cyclists, not fewer; that a bike lane will slow vehicle traffic to a crawl; and even that safe bike lanes are only for “the privileged.”
As a result of the facilitated conversations, SDOT reportedly presented two options for moving forward: The “contracted design” (to which the Move Seattle Levy report, above, refers), with a protected bike lane on one side of the street, an unprotected bike lane on the other, two travel lanes, and one lane of parking; and an “alternative,” which includes no bike lanes, a lane of parking, two travel lanes, and a center turn lane. The “alternative,” interestingly, would get rid of the same amount of parking as the protected bike lane option; the only difference between it and the way 35th Avenue NE is currently configured is the new center turn lane.
SDOT directed questions about the new 35th Avenue option to the mayor’s office, which has not responded substantively to requests for comment made on Monday and Tuesday.
Meanwhile, I spoke with several bike advocates who participated in the mediation. They say they remain optimistic that 35th Avenue NE will get bike lanes eventually, but were concerned about the precedent created by the mediation process, which Durkan and Northeast Seattle council member Rob Johnson initiated after getting thousands of emails opposing the project. Liam Bradshaw, a member of the pro-bike-lane group Safe 35th Avenue NE, says the bike lane project “sat and festered and we had this whole debate. There was nobody who would say outright that we were going to build it the way it was drawn.” Bradshaw says the lack of a permanent SDOT director contributed to the delay. “I don’t fault the mayor for not making a decision—I fault the mayor for not appointing an SDOT director,” he says.
Advocates for the bike lane have started a Change.org petition urging the city to “Complete the 35th Ave NE safety project now!” Durkan is supposed to announce a decision on the project by the end of the year.